B513 public spaces renovation - Rénovation des espaces publics du B513

Duration

30 Oct 2017 to 21 Dec 2017

Description

Dear colleagues,

 

Works have started in B513 this week and more is coming until the end of 2017 at least

 

Phase 1: started on Monday 30th October
Painting works in the corridor between B31 and B513 but will not prevent the use of the corridor

 

Phase 2: should start Monday 6th November, ending on Friday 17th November

The main stair case will be blocked from the 2nd floor down to the basement. Please use the external stair cases or the elevator. In the event of an evacuation alarm, please only use the external stair cases [see temporary evacuation plans below [1], [2], [3], ground floor not affected by any evacuation changes]

The groups visiting the building were asked to use the external stair cases as well to access the Data Centre Visit Point on the first floor. They were informed to ask their group to keep quiet as they will be walking through office spaces

 

Phase 3: should start in parallel of phase 2 on Monday 13th November, ending on Friday 24th November

The main stair case will still be blocked. Please keep using the external stair cases or the elevator. In the event of an evacuation alarm, still only use the external stair cases.

The groups visiting the building were asked to use the external stair cases as well to access the Data Centre Visit Point on the first floor. They were informed to ask their group to keep quiet as they will be walking through office spaces

In addition the visit gallery 513-1-204 will be inaccessible and the second evacuation door in the Data Centre Visit Point will be blocked. Safety limitations will have to be applied and groups will have to be limited to 19 people maximum (18 visitors + 1 guide). The meeting room 513-1-024 will be closed as evacuation routes will be reduced [see summary on 513-1 map below [4] ]

 

Finition : Monday 11th December, ending on Thursday 21th december

The main noisy activities including drilling and painting are completed. Visit room and meeting rooms are availables.

There are several small painting finitions and cabling, the Buzziskin to install on the wall (acoustic material self sealing) and mostly the museum room to refurbish before the IT Christmas party.

 

 

Thanks for your understanding

Anthony GROSSIR – B513 TSO

Alain GENTIT - B513 TSO

 

 

Files displayed as specified below

[1] B513-S temporary emergency evacuation path

[2] B513-1 temporary emergency evacuation path

[3] B513-2 temporary emergency evacuation path

[4] 513-1 works details

Back to...

Building(s) affected

513

Contact

For any safety matters, contact the Territorial Safety Officer (TSO) of the building concerned. Find your TSO.

Posted on

26 Oct 2017

Last updated

12 Dec 2017

You are here